One unit first. Then the same unit, again.
Our portfolio is a development pipeline. Nothing in it is operational, and every phase carries the stage it has actually reached.
Phase 1
FOAK Andalusia
In developmentNear Seville, Spain · First-of-a-kind
Technology
Off-grid photovoltaics (15 MW), battery (7.5 MWh), electrolysis (6.0 MW), Direct Air Capture (3,200 tpa CO₂) and methanol synthesis (5,000 tpa) integrated in one standardised unit.
Timeline and offtake
Construction targeted 2027-2028; commissioning and first methanol targeted Q1 2029. Phase 1 output is intended for distributors and blend-in buyers while institutional offtake is negotiated against pooled Phase 2 and 3 volume.
Pipeline
Phase 2 · 2028-29
Four unitsProcess optimisation across replicated units and the first pooled offtake volume.
Planned
Phase 3 · 2029-30
Sixteen units · 100 MW+ totalHub scale, with institutional offtake contracted against pooled volume.
Target
Critical path Permitting sits on the critical path. Our phase dates assume permitting runs in parallel with supplier contracting from early 2027.